Construction at RWCU

Red Wing Credit Union history

Phase two of our building project has just begun. We will be adding a 2-story addition which requires a temporary main entrance while construction takes place. We expect construction to be complete in early January 2026. Check back here regularly for updates on the progress.

Throughout this phase of the construction process, our lobby and drive thru will remain open for business as usual.

 

Important Service Notes:

  • The Lobby is open for business as usual. Please enter through the temporary main front doors – look for signs.
    Lobby Hours are M-F 8:30 AM – 4:30 PM; Sat. 8:30 AM – 12 Noon
     
  • Our Drive Thru is fully operational at our main location.  To access, use the North Service Drive entrance, near Sargent’s Nursery. Traffic flow is reversed from the old drive thru.
    Drive Thru Hours are M-F 8:30 AM – 5:00 PM, Sat. 8:30 AM – 12 Noon
     
  • Our Night Drop is housed within the ATM Kiosk (located at the main building, 3303 N. Service Drive).
     
  • The ATM is available in its new, permanent location within the newly remodeled drive thru area, under the canopy. To access, please enter at the North Service Drive entry near Sargent’s Nursery. 

PHASE ONE: Drive Thru Reconstruction

rwcu construction drive-thru render

Our first phase of construction will begin very soon and focus on the complete reconstruction of our drive thru area. Our current infrastructure simply does not support the volume of traffic that occurs daily. We will be replacing all existing hardware, including the ATM, and expanding the lane size to accommodate larger vehicles. The canopy will be expanded to better shield the area from sun, rain, and snow. In addition, the traffic pattern will be reversed to improve flow and prevent traffic back up.

During this time, our drive up will operate out of the facility at 3151 S. Service Drive, immediately behind Walgreens. We expect the drive-up reconstruction to be complete by the end of 2024 when we will resume drive-up service at our newly reconfigured main office drive up.

Throughout the construction process, our lobby will remain open for transactions, member service, and loans.

PHASE TWO: Building Expansion

rwcu construction building expansionThis spring, we will also begin a project to expand our building. We will be adding a 2-story addition around our main entry and current handicap spaces. Temporary access will be established while construction takes place in the new area. We expect construction to be complete by the end of 2025. The new space will expand member contact areas and add needed space for administrative services including training, meeting, storage, and employee services. The overall site will be reconfigured to add additional parking and improve traffic flow. With nearly 30 staff members on-site daily, the additional space will greatly support their daily efforts to serve you.

Construction Photos

This is sample image #1

PHASE 2, WEEK ONE – Full view of the main building, with signs marking the new temporary entrance.

This is sample image #1

PHASE 2, WEEK ONE – View of the temporary main entrance. Just follow the signs.

This is sample image #1

PHASE 2, WEEK ONE – The beginning of demolition..

This is sample image #1

PHASE 2, WEEK ONE – A view of the first full day of demolition.

This is sample image #1

Week Fourteen – Work continues in the drive thru area. These photos were taken from inside our building.

This is sample image #1

Week Fourteen – Moving old equipment to make room for the new!

This is sample image #1

Week Fourteen – Work continues in the drive thru area despite the cold. The drive thru was enclosed for brick and other finish work.

This is sample image #1

Week Fourteen – Please use and reference this map for the updated layout. Please note: traffic will flow in the opposite direction of the old drive thru. The new and permanent entrance for the ATM, Night Drop, and Drive Thru lanes will be the North Service Drive entrance near Sargent’s Nursery. Watch for signs to help guide you once re-opened!

This is sample image #1

Week Nine – Work continues in the drive thru area. These photos were taken from inside our building. Steel beams are going up for the new canopy.

This is sample image #1

Week Nine – Work continues on the new canopy for the drive thru area.

This is sample image #1

Week Nine – Securing the beams for the new drive thru canopy.

This is sample image #1

Week Nine – The drive thru is really starting to take shape now!

This is sample image #1
Week Six – Work in the drive thru area continues. Prepping for concrete to be poured.
This is sample image #1

Week Six – Work in the drive thru area continues. Just starting to pour concrete for the drive thru islands here.

This is sample image #1
Week Six – Work in the drive thru area – concrete is being poured and formed for the drive thru islands. This photo was taken from inside our building.
This is sample image #1

Week Three – Work continues in the drive thru area. These photos were taken from inside our building.

This is sample image #1

Week Three – Work continues in the drive thru area. These photos were taken from inside our building.

This is sample image #1

Week Three – Work continues in the drive thru area. These photos were taken from inside our building.

This is sample image #1

Week Three – Work continues in the drive thru area. These photos were taken from inside our building.

This is sample image #1

Week Two – Our ATM has moved to its temporary location on the Highway 61 side of our main building. Just follow the signs and enter thru the old drive thru exit (near Sargent’s Nursery). The ATM is available 24/7.

This is sample image #1

Week Two – Our ATM has moved to its temporary location on the Highway 61 side of our main building. Just follow the signs and enter thru the old drive thru exit (near Sargent’s Nursery). The ATM is available 24/7.

This is sample image #1

Week Two – The Drive Thru canopy demolition has begun…in progress photo from Wednesday, October 23.

This is sample image #1

Week Two – The Drive Thru canopy demolition has begun…in progress photo from Wednesday, October 23.

This is sample image #1

Week One – The Drive Thru canopy has been removed. Clean up and preparation for the next steps in progress on Thursday, October 24.

This is sample image #1

Week One – Drive Thru and Night Drop Services have moved to a temporary location at 3151 South Service Drive. Drive Thru hours are Monday – Friday: 8:30AM – 5:00PM, and Saturday 8:30AM – 12:00PM Noon.

This is sample image #1

Week One – Fencing went up this morning for demo work that will be done to our front sidewalk and in preparation for our new main entrance. Drive Thru service has moved to a temporary location during construction – you can access Drive Thru & Night Drop Services at 3151 South Service Drive, Red Wing.

This is sample image #1

Week One – Our main entrance is fully accessible and ready for business. Our Lobby is open!

This is sample image #1

Week One – Our ATM has been moved to its temporary location on the Highway 61 side of our building. The ATM is available 24/7 and accessible by entering thru the old drive thru exit (near Sargent’s Nursery).